Friday, May 8, 2009

Day 1 - (5th May) Removal of cabinets and hacking starts !

Uncle was very punctual. I was sending my family to my mum's place to stay at around 8am and I saw uncle's signature green van when I was turning out of the car park. As soon as I dropped off my family, I managed to meet Uncle to bring him and his workers (3 of them up).

My demolition and removal team consists of 3 person on Day 1 - Singh, Silva and Freddy. I called Singh Superman because he's a really efficient worker and he don't need to wear any protection while hacking. Progress was initially fast but they hit a snag because part of my wall was previously done up by my ex-owner and they used very strong adhesive to stick the tiles. As a result, they couldn't complete the hacking within 1 day.

Uncle came twice that day. In the morning to give instructions and in the afternoon around 2pm to check on the progress. He told me that tiles and materials can come the next day and tilings should be able to commence (which unfortunately didn't materialise because the delivery of the tiles and sand were delayed !)

Pictures from Day 1:

Laying of cardboard protection sheets on the floor

Uncle showing the workers how and what to remove

Uncle hacked one part of the wall tiles to check the condition of the wall

The demolition team removing the cabinets

All the removed cabinets and kitchen carpentry

Kitchen floor tiles hacked

Hacking of toilet floor tiles

The stubborn kitchen wall tiles that caused the delay

Kitchen wall tiles partially hacked